Mobile County School District

Mobile, Alabama

With more than a dozen simultaneous projects including two new campuses, Mobile County Public Schools (MCPS) needed a diverse group of architects working concurrently to deliver speed to market. HPM brought structure in motion by coordinating the preconstruction efforts all while providing accurate and consistent reporting to the school’s public-access website.

Turning a Challenge into a Success
HPM initially identified a suitable location which would utilize Citronelle High School’s existing facilities. However, prior to design completion, soil conditions for that building site were found to be unacceptable and required swift and precise planning to locate available land. Our HPM team undertook an enormous effort to find acceptable land to purchase and keep the new construction project on track for a spring 2016 completion. This potential setback provided HPM with an opportunity to provide value to our client and share sound solutions to overcome a potential obstacle to the on-time completion of the project.

Project Scope and Size

New Construction
Citronelle High School
Fournier-Chastang K-8 School
New Facilities
Multi-purpose buildings for 7 elementary schools
New auditorium for Leflore High School
New science wing for Burns Middle School
Major Renovations
Lott Middle School
Murphy High School
Phillips Preparatory School
Tanner Williams Elementary
Mae Eanes Middle School
Dauphin Island Elementary
Barton Academy



Project Details

$100 million program
A&E/consultant selection
18 projects
Mass qualifications and RFPs
Complete in 60 days
Saved $ vs. target cost
Savings= 1/2 HPM total cost

Owner

Mobile County Public Schools
Reference:
Martha Peek
Superintendent

Architect

Various

HPM Services

Preconstruction
Construction Administration
Project Management